Carnegie Clean Energy Deploys CETO Buoyant Actuator off Spanish Coast

Carnegie Clean Energy Deploys CETO Buoyant Actuator off Spanish Coast

Carnegie Clean Energy deploys its CETO wave-energy actuator off Spain, paving the way for a grid-connected trial in 2027.

Nik Hill
Nik HillJournalist
· 2 min read
In this storyCCE
In briefAt-a-glance3 takeaways
  • 01CETO actuator deployed at Spain’s BiMEP test site.
  • 02Stage 1 tests offshore logistics and mooring.
  • 03Grid-connected prototype planned for spring 2027.

Carnegie Clean Energy (ASX: CCE) has deployed its CETO Buoyant Actuator at an offshore test site in Spain, completing a key installation step in its wave-energy development program.

The device is moored at the Biscay Marine Energy Platform (BiMEP) off Armintza in the Basque Country following assembly and transport from the Port of Bilbao.

The short Stage 1 campaign is designed to test marine logistics, authorisations, and the behaviour of the CETO BA during towing and mooring in real ocean conditions.

Carnegie is preparing for a second stage involving deployment of the fully integrated CETO system and connection to the electricity grid in European spring 2027.

Completion of the Stage 1 deployment activities also triggers funding milestones under the ACHIEVE program, supporting the work required for the next development phase.

Advertisement

Offshore Assembly and Installation

Three modular sections manufactured locally in the Basque Country were transported to Bilbao and assembled beside the quay before the completed CETO BA was lowered into the water by crane.

The device was then docked alongside the quay ahead of its tow to Carnegie’s pre-permitted offshore berth at BiMEP on Saturday.

At the offshore site, crews connected it to a specially installed anchor and mooring system after coordinating vessels, towing procedures, and the mooring hook-up.

The operation required clearances covering quayside assembly, heavy lifting, port transit and offshore installation from the relevant maritime and port authorities.

Carnegie considers those practical approvals and logistics processes important preparation for the more complex installation and commissioning activities planned for Stage 2.

Advertisement

First Campaign Lessons

The initial deployment is deliberately brief, with retrieval and the return tow to Bilbao to be scheduled according to suitable weather and vessel availability.

This retrieval will provide another opportunity to test the marine procedures and local supply chain arrangements needed to bring the equipment safely ashore.

Carnegie’s chief technology officer led the offshore activities, drawing on experience with the company’s earlier CETO array deployment in Australia and subsequent technology design.

The company expects the experience gained by its wider team to improve its capability to manage future offshore campaigns in the Basque Country.

Advertisement

2027 Grid Connection Planned

After retrieval, the BA will remain onshore over the European winter while the power takeoff modules undergo final local testing alongside the Electrical Module.

Those tests will simulate ocean operating conditions and assess mechanical, electrical, control and communications functions before the components are integrated offshore.

The fully assembled CETO prototype is scheduled to return to BiMEP for grid-connected deployment during European spring 2027, when weather is expected to be more suitable for initial commissioning.

“While this is just the first stage of offshore campaign, the experience gained from this short deployment has increased our team’s capabilities and put us in a much stronger, more certain position as we push toward our full grid-connected Stage 2 deployment in European spring 2027,” chief executive officer Jonathan Fiévez said.

“This is an ambitious project given the large technology leaps we’re taking so executing it in stages and conducting substantial onshore testing are important to manage risk.”

Subscribe · daily wire

Get the wire before the market opens.

The ASX small-cap stories that matter, filed before 9am AEST. Curated by the Small Caps desk.

Join 100,000+ investors. Unsubscribe anytime.
Nik Hill
About the author

Nik Hill

Journalist
View all articles

More like this

View all latest