- 01FRS secures cyanide and ore-handling contracts.
- 02Edna May has 60,000t ready; first pour targets Dec 2026.
- 03Lake Johnston stockpile tops 180,000t.
Forrestania Resources (ASX: FRS) has signed a long-term reagent supply agreement and awarded an ore-handling contract as it prepares to restart production at its Edna May gold mine in Western Australia.
The arrangements cover sodium cyanide for gold recovery and the loading of ore into the crusher, two requirements for the transition from plant commissioning to processing.
Approximately 60,000 tonnes of ore is already available at Edna May, with first ore processing approaching and the first gold pour targeted for December 2026.
The miner has also opened a Kalgoorlie operational office as it builds the workforce and infrastructure needed to operate across Edna May and Lake Johnston, along with a new corporate website to support shareholder updates, project information, and recruitment during that transition.
Plant Restart Support
Forrestania executed the sodium cyanide agreement with Australian Gold Reagents, establishing long-term access to a chemical used in recovering gold from processed ore.
The company awarded its ore loading and crusher feed work to Campbell Gold Haulage, known as Campbells, which has begun mobilising personnel and equipment.
Campbells already holds the road train contract, bringing haulage and ore loading activities under the same contractor at the run-of-mine (ROM) stockpiles.
That arrangement is intended to improve the coordination of ore handling and plant feed at both Edna May and Lake Johnston, with Forrestania moving from dry to wet commissioning as it prepares to process ore at Edna May for the first time under the restart.
Ore Inventories Build
Alongside the material ready at Edna May, Lake Johnston holds more than 180,000t of ore and its inventory continues to grow.
The Lake Johnston ROM stockpile is approaching full capacity, placing ore availability alongside reagent supply and material handling in Forrestania’s operational preparations.
Forrestania’s broader plan centres on sourcing ore from deposits and development assets within haulage distance of its processing infrastructure, with Edna May the immediate production priority and Lake Johnston being developed as a second processing hub within the group’s WA operations.
“These initiatives represent important milestones in the systematic build-out of Forrestania’s operating platform as we progress toward production at Edna May,” executive chair David Geraghty said.
“Our focus is on ensuring every element of each operation is in place for a successful transition to production.”
Expanded Kalgoorlie Hub
The newly established Kalgoorlie office will provide an operating base for the group’s growing mining workforce and will be shared with principal mining contractor MEGA Resources.
New general manager of mining Darren Gaby will lead the office and the company’s mining operations, drawing on more than 30 years of operational and development experience in the Western Australian Goldfields.
Gaby previously led development of the Jaurdi gold project from construction into production and has worked in senior operational and technical roles at established gold operations.
The permanent regional presence is designed to support work across Forrestania’s expanding projects as it moves from gold development into production.